Why Did Oracle (ORCL) Stock Fall on Oct 8, 2026? OpenAI Revenue Report and Trucked Gas
Oracle closed down 5.48% after reports, 21 seconds apart, on trucked gas for Project Jupiter and OpenAI's $50 billion annualized revenue.
- Oracle closed at $135.69 on October 8, 2026, down 5.48%, after two reports reached the MoveSurge news feed 21 seconds apart.
- The Financial Times reported OpenAI's annualized revenue at about $50 billion; Oracle has a five-year, $300 billion OpenAI contract starting in 2027.
- A separate report said Oracle is weighing trucked natural gas for Project Jupiter, whose gas pipeline is delayed to February 1, 2027.
Reaction by asset (real prices)
| Asset | 2m before | At release | +1m | +10m | +1m % | +10m % |
|---|---|---|---|---|---|---|
| ORCL | 140.37 | 140.37 | 137.61 | 135.62 | -1.97% | -3.38% |
Oracle stock fell 5.48% on Thursday, October 8, 2026, closing at $135.69, after two reports about its artificial-intelligence build-out reached the MoveSurge news feed 21 seconds apart. At 12:43:21 ET came a report that Oracle is considering trucking natural gas to its Project Jupiter data center in New Mexico, and at 12:43:42 ET the Financial Times report that OpenAI's annualized revenue was about $50 billion, roughly $20 billion below figures investors had been circulating.
Oracle traded at $140.37 just before the first headline, at $137.60 a minute later, down 1.97%, and at $135.62 ten minutes later, down 3.38%; after fourteen minutes it was at $135.07, 3.78% lower. With the two headlines so close together the move cannot be split between them. CoreWeave, another OpenAI supplier with no part in Oracle's gas plans, fell 7.77% on the day.
Why the OpenAI figure matters to Oracle
OpenAI's revenue pays for the computing capacity it has contracted, and Oracle signed a five-year, $300 billion cloud contract with OpenAI in 2025 that begins in 2027. The FT figure was lower because OpenAI reports annualized revenue without the sales its cloud partners make, while the numbers in circulation had been adjusted to match Anthropic, which counts them. Our report on the OpenAI revenue figure and the moves in other AI stocks has the full comparison.
Project Jupiter's power problem
Project Jupiter is a campus of about 2.5 gigawatts in Doña Ana County, New Mexico. The Green Chile pipeline meant to supply its gas has been delayed to February 1, 2027, and on September 24 Oracle sent a force majeure notice over the power-supply risk to Stack Infrastructure, the Blue Owl Capital unit developing the site, while saying Jupiter remained on its planned schedule. The plan reported on October 8 would let early stages of the campus run on compressed natural gas delivered by truck before the pipeline is in service. Oracle already uses trucked gas at projects in Utah and Texas, supplied by Certarus and VoltaGrid, and it costs roughly four times as much as gas delivered by pipeline.
The backlog behind the build-out
On September 10 Oracle reported fiscal first-quarter revenue up 30% at $19.3 billion, with cloud infrastructure revenue up 121% at $7.4 billion. Remaining performance obligations, the contracted revenue Oracle has yet to recognize, rose $209 billion from a year earlier to $664 billion, $26 billion more than three months before, and the company said it booked more than $30 billion of additional AI cloud contracts in the quarter.

Recent Oracle developments
- October 8, 2026: reports that Oracle is weighing trucked natural gas for Project Jupiter and that OpenAI's annualized revenue is about $50 billion; the stock closed down 5.48%.
- September 24, 2026: Oracle sends a force majeure notice over power supply at Project Jupiter to Stack Infrastructure.
- September 10, 2026: fiscal first-quarter results, with remaining performance obligations of $664 billion and cloud infrastructure revenue up 121%.
- August 2026: a regulatory filing shows the Green Chile gas pipeline for Project Jupiter delayed to February 1, 2027.
- August 13, 2026: Oracle and Amazon Web Services expand their agreement to move customers onto Oracle AI Database@AWS, with Exadata Database Service on Exascale Infrastructure generally available in 22 AWS regions.
Why did Oracle stock fall on October 8, 2026?
Oracle closed down 5.48% at $135.69 after two reports 21 seconds apart: that it is weighing trucked natural gas for its Project Jupiter data center, and the Financial Times report that OpenAI's annualized revenue is about $50 billion. Oracle has a five-year, $300 billion cloud contract with OpenAI that begins in 2027.
What is Oracle's Project Jupiter?
A data center campus of about 2.5 gigawatts in Doña Ana County, New Mexico. The pipeline meant to supply its gas has been delayed to February 1, 2027.
Why did Oracle declare force majeure on Project Jupiter?
On September 24, 2026 Oracle sent a force majeure notice to Stack Infrastructure, the Blue Owl unit developing the site, over the risk to its power supply. Oracle said the project remained on its planned schedule.
How big is Oracle's contract backlog?
Remaining performance obligations were $664 billion at August 31, 2026, up $209 billion from a year earlier, Oracle reported on September 10, 2026.
Sources
-
Oracle Moves Gas by Trucks to Avoid Data Center Power Delays
— SupplyChainBrain
Trucked compressed natural gas would let early stages of Oracle data centers run before pipelines arrive; Certarus in Utah and VoltaGrid in Texas; roughly four times the cost of pipeline gas.
-
Oracle (ORCL) Considers Trucked Natural Gas for New Mexico Data Center Amid Pipeline Delays
— GuruFocus
Oracle exploring trucked gas for Project Jupiter; the pipeline's in-service date pushed to February 1, 2027.
-
OpenAI's revenue is reportedly $20 billion less than previously projected
— TechCrunch
Per the FT, OpenAI's annualized revenue was about $50 billion, about $20 billion below earlier estimates; Anthropic counts cloud-partner sales, OpenAI does not.
-
Nvidia, Oracle, CoreWeave and other AI stocks sink on OpenAI revenue report
— CNBC
Oracle shares fell nearly 6% on October 8 after the OpenAI revenue report.
-
Oracle triggers force majeure on data centre project over power delays, source says
— BNN Bloomberg
Force majeure notice sent on September 24 to Stack Infrastructure, the Blue Owl unit developing Project Jupiter; Oracle said the project remains on schedule.
-
Oracle Announces Q1 Results Driven by Triple Digit Growth in Cloud Infrastructure Revenues
— Oracle
Revenue up 30% to $19.3 billion; cloud infrastructure up 121% to $7.4 billion; RPO $664 billion, up $209 billion year over year and $26 billion from Q4; over $30 billion of new AI cloud contracts.
Never miss the next market-moving story
Follow the core market-moving feed across equities, macro, currencies and commodities. Your subscription includes price moves after the news, search, watchlists, alerts and research tools.
Create free accountGo real time Watch live headlines -- free